Projects

Our Engineering Portfolio

Njowazi Limited is an ISO 9001: 2008 Certified Company. It is a team of Engineers and Technicians with over 30 years of experience in Construction and Engineering. Over the years, Njowazi experience had touched on many projects in different parts of the world.

We have also worked with ZAISCO Construction and Engineering which is an ISO 9001: 2008 Certified Company, whom we have sub-contracted to work on some projects. A timeline of the projects we have done till the present time is outlined below.

March 2024 to Present

Additional Mechanical Repair Works to Tank 102

Client: Kenya Petroleum Refineries Limited

Contract Value: USD 200,000

Mechanical repair works to a tank 102, which is used for oil storage.

Read more
November 2023 to March 2024

Project: Mechanical Rehabilitation to ago Tank 302

Client: VTTI Kenya Limited

Contract Value: Ksh 12 million

Open tank manholes and gas free the tank. - Clean and grit blast tank for mechanical inspection - Cut and remove the existing old single deck floating roof. - Renew annular plates with tank pad and tank pad shoulder. - Fabricate and install new double deck floating roof including refurbishing of corroded parts of the tank. - Grit blast and paint the tank - Hydro-test the tank and commission.

Read more
April 2023 to October 2023

Project: Mechanical Rehabilitation to ago Tank 302

Client: VTTI Kenya Limited

Contract Value: Ksh 11.4 million

Open tank manholes and gas free the tank. - Clean and grit blast tank for mechanical inspection - Cut and remove the existing old single deck floating roof. - Renew annular plates with tank pad and tank pad shoulder. - Fabricate and install new double deck floating roof including refurbishing of corroded parts of the tank. - Grit blast and paint the tank - Hydro-test the tank and commission.

Read more
January 2023 to April 2023

Tank 117 and 118 Isolation and Cleaning Services

Client: Tullow Kenya B.V Limited

Contract Value: Ksh 10 million

Isolation and cleaning services for tanks 117 and 118 for Tullow Kenya B.V Limited

Read more
January 2022 - March 2023

Mechanical Rehabilitation to ago Tank 103, 105, 106, 104, 102, 101 and 201

Client: VTTI Kenya Limited

Contract Value: USD 700,000

Open tank manholes and gas free the tank. - Clean and grit blast tank for mechanical inspection - Cut and remove the existing old single deck floating roof. - Renew annular plates with tank pad and tank pad shoulder. - Fabricate and install new double deck floating roof including refurbishing of corroded parts of the tank. - Grit blast and paint the tank - Hydro-test the tank and commission.

Read more
August 2021 to October 2021

Mechanical Rehabilitation to ago Tank 105

Client: VTTI Kenya Limited

Contract Value: Ksh 10 million

Open tank manholes and gas freeing the tank. - Clean and grit blast tank for mechanical inspection - Cut and remove the existing old single deck floating roof. - Renew annular plates with tank pad and tank pad shoulder. - Fabricate and install new double deck floating roof including refurbishing of corroded parts of the tank. - Grit blast and paint the tank. - Hydro-test the tank and commission

Read more
April 2021 to August 2021

Mechanical Rehabilitation to ago Tank 104

Client: VTTI Kenya Limited

Contract Value: Ksh 7 million

Open tank manholes and gas free the tank. - Clean and grit blast tank for mechanical inspection - Cut and remove the existing old single deck floating roof. - Renew annular plates with tank pad and tank pad shoulder. - Fabricate and install new double deck floating roof including refurbishing of corroded parts of the tank. - Grit blast and paint the tank - Hydro-test the tank and commission.

Read more
April 2021 to September 2021

Mechanical Rehabilitation to ago Tank 115

Client: Kenya Petroleum Refineries Limited

Contract Value: USD 500,000

Open tank manholes and gas free the tank. - Clean and grit blast tank for mechanical inspection - Cut and remove the existing old single deck floating roof. - Renew annular plates with tank pad and tank pad shoulder. - Fabricate and install new double deck floating roof including refurbishing of corroded parts of the tank. - Grit blast and paint the tank - Hydro-test the tank and commission.

Read more
September 2019 to June 2020

Mechanical Rehabilitation of Tank 210

Client: Kenya Petroleum Refineries Limited

Contract Value: USD 300,000

Open tank manholes and gas free the tank. - Clean and grit blast tank for mechanical inspection - Cut and remove the existing old single deck floating roof. - Renew annular plates with tank pad and tank pad shoulder. - Fabricate and install new double deck floating roof including refurbishing of corroded parts of the tank. - Grit blast and paint the tank - Hydro-test the tank and commission.

Read more
November 2018 to March 2019

Repair/Replacement of 1000mm Sewer Line

Client: VTTI Kenya Limited Kipevu, Mombasa

Contract Value: Ksh 75,475,376

Repair and installing of new 1000mm sewer pipeline

Read more
July 2018 to August 2018

Sludge Removal/Cleaning of Tanks and Pipeline Installation at KPA Area-K.P.R.L/K.P.C

Client: Kenya Petroleum Refineries Limited/Kenya Pipeline

Contract Value: Ksh 10,150,000

Tank Cleaning/Pipeline Installation

Read more
July 2018 to August 2018

Maintenance of 8" LPG, 8" M Product and 16" FOL at KPA Area-KPRL/KPC

Client: Kenya Petroleum Refineries Limited/Kenya Pipeline

Contract Value: Ksh 5.4 million

Maintenance of 8" LPG, 8" M Product and 16" FOL at KPA Area-KPRL/KPC

Read more
May 2018 to June 2018

Sewer Line Phase 1 Repair VTTI - MSA

Client: VTTI Kenya Limited

Contract Value: Ksh 1,153,040

Sewer Line Phase 1 Repair VTTI - MSA

Read more
October 2017 to April 2018

Tank Repair, Grit Blasting and Painting Tank 301 PS 14

Client: Kenya Pipeline Company Limited

Contract Value: Ksh 108,400,000

Open tank manholes and gas free the tank. - Clean and grit blast tank for mechanical inspection - Cut and remove the existing old single deck floating roof. - Renew annular plates with tank pad and tank pad shoulder. - Fabricate and install new double deck floating roof including refurbishing of corroded parts of the tank. - Grit blast and paint the tank - Hydro-test the tank and commission.

Read more
June 2017 to September 2017

Cleaning, Blasting and EPOXY Lining of Tank 702, PS 9 Embakasi, Nairobi

Client: Kenya Pipeline Company Limited

Contract Value: Ksh 10,440,000

Tank Cleaning - Grit blasting - Internal & external painting of shell and roof

Read more
April 2017 to July 2017

Replacement of the 24" Crude Oil Line K.P.R.I

Client: Kenya Petroleum Refineries

Contract Value: USD 130,000

Construction of pipe support. - Laying of 24” pipeline and tie in at K.P.R.L. and main terminal in Mombasa

Read more
April 2017 to July 2017

Fabrication of the ROM-PUMP Unit

Client: BASE Titanium Kenya Limited

Contract Value: USD 100,000

Fabrication of the ROM-PUMP Unit

Read more
Jan 2017 to March 2017

Mechanical Rehabilitation to Tanks 117, 118 and 119

Client: Kenya Petroleum Refineries

Contract Value: USD 70,000

Open tank manholes and gas free the tank. - Clean and grit blast tank for mechanical inspection - Cut and remove the existing old single deck floating roof. - Renew annular plates with tank pad and tank pad shoulder. - Fabricate and install new double deck floating roof including refurbishing of corroded parts of the tank. - Grit blast and paint the tank - Hydro-test the tank and commission

Read more
September 2014 to March 2015

Mechanical Rehabilitation to PMS Tank

Client: Libya Oil Kenya Limited

Contract Value: USD 200,000

Open tank manholes and gas free the tank. - Clean and grit blast tank for mechanical inspection - Cut and remove the existing old single deck floating roof. - Renew annular plates with tank pad and tank pad shoulder. - Fabricate and install new double deck floating roof including refurbishing of corroded parts of the tank. - Grit blast and paint the tank - Hydro -test the tank and commission

Read more
September 2014 to June 2015

Mechanical Rehabilitation to ago Tank 10

Client: Libya Oil Kenya Limited

Contract Value: USD 200,000

Open tank manholes and gas free the tank. - Clean and grit blast tank for mechanical inspection - Cut and remove the existing old single deck floating roof. - Renew annular plates with tank pad and tank pad shoulder. - Fabricate and install new double deck floating roof including refurbishing of corroded parts of the tank. - Grit blast and paint the tank - Hydro-test the tank and commission

Read more
July 2014 to March 2015

ROOFING - MOMBASA LOBP, FILLING HALL & ADJOINING STRUCTURES.

Client: LIBYA OIL KENYA LTD

Contract Value: USD 100,000

Supply of Labour, equipment & materials to carry out replacement of Aluminum roofing works on LOBP, Filling Hall.

Read more
December 2012 to November 2013

MECHANICAL REHABILITATION TO 14 TK. 201.

Client: KENYA PIPELINE COMPANY

Contract Value: USD 700,000

Open tank manholes and gas free the tank. - Clean and grit blast tank for mechanical inspection - Cut and remove the existing old single deck floating roof. - Renew annular plates with tank pad and tank pad shoulder. - Fabricate and install new double deck floating roof including refurbishing of corroded parts of the tank. - Grit blast and paint the tank - Hydro-test the tank and commission

Read more
July 2011 to November 2012

MECHANICAL REHABILITATION TO (HFO) POWER FUEL OIL TANKS

Client: KENYA PETROLEUM REFINERIES

Contract Value: USD 213,000

- Supply of materials & erection of new tanks. - Clean and grit blast tank for mechanical inspection - Grit blast and paint the tank - Hydro-test the tank and commission.

Read more
July 2011 to November 2012

MECHANICAL REHABILITATION TO T.119.

Client: KENYA PETROLEUM REFINERIES

Contract Value: USD 259,000

Open tank manholes and gas free the tank. - Clean and grit blast tank for mechanical inspection - Cut and remove the existing old single deck floating roof. - Renew annular plates with tank pad and tank pad shoulder. - Fabricate and install new double deck floating roof including refurbishing of corroded parts of the tank. - Grit blast and paint the tank - Hydro - test the tank and commission.

Read more
November 2010 to July 2011

MECHANICAL REHABILITATION TO T. 602

Client: KENYA PIPELINE COMPANY.

Contract Value: USD 850,000

gas freeing and cleaning the tank. - Repair tank pad and bottom plates. - Repair to foam dam and install new roof s e a l . - Repair to top roof deck plate. - Replace all roof legs support & replace pontoon manhole cover. - Repair to walkway, platform and wind g i r d e r . - Grit blast and paint the entire tank internally and externally.

Read more
September 2010 to March 2011

SUPPLY & CONSTRUCT LOADING GANTRY WITH ALL ITS ASSOCIATED PIPING PUMPS AND TIE IN TO EXISTING FACILITIES.

Client: OILIBYA KENYA LTD

Contract Value: USD 220,000

SUPPLY & CONSTRUCT LOADING GANTRY WITH ALL ITS ASSOCIATED PIPING PUMPS AND TIE IN TO EXISTING FACILITIES.

Read more
May 2010 to November 2010

MECHANICAL REHABILITATION TO T. 207.

Client: KENYA PETROLEUM REFINERIES

Contract Value: USD 300,000

Open tank manholes and gas free the tank. - Clean and grit blast tank for mechanical inspection - Cut and remove the existing old single deck floating roof. - Renew annular plates with tank pad and tank pad shoulder. - Fabricate and install new double deck floating roof including refurbishing of corroded parts of the tank. - Grit blast and paint the tank - Hydro-test the tank and commission

Read more
September 2009 to January 2011

MECHANICAL REHABILITATION TO T. 209.

Client: KENYA PETROLEUM REFINERIES

Contract Value: USD 900,000

-Gas free, clean and blast the entire tank - Renew tank pad and bottom plates. - Renew entire single deck floating roof. - Cut, remove and replace shell courses 2, 3 and identified plates on shell course 4. - Carry out weld filling on shell courses 4 and 5 . - Renew guide pole and repair wind girder by weld-filling and inserts. - Install new roof drain, roof seals and roof l e g s . - Renew tank pad shoulder. - Paint tank internally and externally. - Hydro-test the tank and commission

Read more
November 2009 to May 2010

: INSTALLATION OF PREFABRICATED MODULE STRUCTURES.

Client: United Nations (UNSOA)

Contract Value: USD 600,000

Setting out. - Assembly of 2x6, 3x4 prefabricated module s t r u c t u r e s . - Installation of ablution units. - Connection to water, sewerage, electricity and data networking. - Installation of pedestrian gates and watch t o w e r s - Erection of shelves. - Installation of generators.

Read more
July 2009 to October 2011

REPLACEMENT OF F.O & IDO - 8” PIPELINE

Client: OILIBYA KENYA LTD.

Contract Value: USD 130,000

Construction of pipe support. - Laying of 8” pipeline and tie in at S.O.T. and m a i n Oilibya terminal in Mombasa.

Read more
November 2008 to March 2009

SEA CABLE LANDING SITE

Client: EARTHTEC U.S.A

Contract Value: USD 1.2 million

- foundation excavation. - Cast concrete columns and slab - Install 8 container modules. - Run 200 meters of ducting & inter-ducting including sea cabling.

Read more
January 2008 to January 2009

MECHANICAL REHABILITATION TO T. 502

Client: KENYA PIPELINE COMPANY

Contract Value: USD 1.2 million

gas freeing and cleaning the tank. - Repair tank pad and bottom plates. - Repair to foam dam and install new roof s e a l . - Repair to top roof deck plate. - Replace all roof legs support & replace pontoon manhole cover. - Repair to walkway, platform and wind g i r d e r . - Grit blast and paint the entire tank internally and externally.

Read more
March 2009 to June 2008

MECHANICAL REHABILITATION TO T. 2701

Client: KENYA PETROLEUM REFINERIES LIMITED

Contract Value: USD 75,000

- gas free and cleaning tank. - Repair to 1st 2nd shell course. - Repair to roof plate. - Paint tank internally and externally.

Read more
November 2007 to August 2008

MOMBASA/NAIROBI PIPELINE RECOATING & SLEEVING PHASE III

Client: KENYA PIPELINE COMPANY

Contract Value: USD 1.6 million

- gas free and cleaning tank. - Repair to 1st 2nd shell course. - Repair to roof plate. - Paint tank internally and externally.

Read more
November 2007 to August 2008

MOMBASA/NAIROBI PIPELINE RECOATING & SLEEVING PHASE I.

Client: KENYA PIPELINE COMPANY

Contract Value: USD 1.3 million

the work involved, repairing the old pipeline (wrapping and sleeving) where necessary. The work was from km (0) to km (88).

Read more
November 2006 to July 2007

CONSTRUCTION OF 16” UNDERGROUND & ABOVE GROUND FUEL OIL LINE 2.5 KM. LONG.

Client: KENYA PETROLEUM REFINERIES LIMITED

Contract Value: USD 550,000

take delivery of client supplied pipe. - Excavate, weld and lay underground p i pe . - Fabricate, install concrete foundation for above ground pipe. - Blast & paint above ground pipes. - Fabricate & install pipe and slippers. - Tie - in pipeline to existing facilities.

Read more
August 2006 to December 2006

MECHANICAL REHABILITATION TO T.113.

Client: KENYA PETROLEUM REFINERIES LIMITED

Contract Value: USD 250,000

- gas free, clean and blast the entire tank bottom. - Repair bottom plates. - Repair entire roof plates - Renew tank pad shoulder. - Paint tank internally and externally.

Read more
August 2006 to December 2006

MECHANICAL REHABILITATION TO T.112.

Client: KENYA PETROLEUM REFINERIES LIMITED

Contract Value: USD 350,000

gas free, clean and blast the entire tank bottom. - Renew tank pad and bottom plates. - Renew entire single deck floating roof. - Renew guide pole and install inserts. - Renew tank pad shoulder. - Paint tank internally and externally.

Read more
May 2006 to April 2007

MECHANICAL REHABILITATION TO T.113.

Client: KENYA PETROLEUM REFINERIES LIMITED

Contract Value: USD 450,000

Gas free, clean and blast the entire tank b o t t o m . - Renew tank pad and bottom plates. - Renew entire single deck floating roof. - Renew guide pole and install inserts. - Renew tank pad shoulder. - Paint tank internally and externally.

Read more
July 2005 to February 2006

MECHANICAL REHABILITATION TO T.111

Client: KENYA PETROLEUM REFINERIES LIMITED

Contract Value: USD 310,000

Gas free, clean and blast the tank bottom. - Renew tank pad and bottom plates. - Renew entire single deck floating roof. - Renew guide pole and install inserts. - Renew tank pad shoulder. - Paint tank internally and externally.

Read more
August 2005 to October 2005

REPLACEMENT OF 16” DIA. PIPE BESIDE KIPEVU BRIDGE

Client: KENYA PETROLEUM REFINERIES LIMITED

Contract Value: USD 40,000

- gas free, clean and blast the entire tank bottom. - Repair bottom plates. - Repair entire roof plates - Renew tank pad shoulder. - Paint tank internally and externally.

Read more
April 2005 to June 2005

MECHANICAL REHABILITATION TO T.113.

Client: KENYA PETROLEUM REFINERIES LIMITED

Contract Value: USD 30,000

Erection of hanging scaffolds. - Removal of existing 16” dia. Pipe. - Installation of new 12” dia. Pipe. - Modification of existing bracket s u p p o r t s . - Paint new 12” dia. Pipeline.

Read more
December 2004 to March 2005

FUEL OIL LOADING FACILITY.

Client: KENYA PETROLEUM REFINERIES LIMITED

Contract Value: USD 90,000

salvage 16” dia. Pipe approx. 400 lm. - Install 16” dia. And 8” dia. Pipelines. - Install concrete pipe supports and s l e e p e r s . - Gas free and clean six number tanks - Paint pipeline.

Read more
June 2004 to December 2004

MECHANICAL REHABILITATION TO T.208.

Client: KENYA PETROLEUM REFINERIES LIMITED

Contract Value: USD 270,000

gas free, clean and blast tank entire bottom. - Replace tank bottom annular plates. - Replace roof plates. - Replace heating coil system. - Paint tank internally & externally.

Read more
November 2003 to March 2005

MECHANICAL REHABILITATION TO T. 110.

Client: KENYA PETROLEUM REFINERIES LIMITED

Contract Value: USD 200,000

gas free, clean and blast the entire tank bottom. - Supply materials jack up tank, remove annular plates, repair foundation and install new annular plates. - Supply materials, cut and replace courses no. 4, 6 and 7th - Paint tank internally & externally.

Read more
June 2004 to December 2004

MECHANICAL REHABILITATION TO T. 306

Client: KENYA PETROLEUM REFINERIES LIMITED

Contract Value: USD 300,000

gas free, clean and blast tank bottom. - Supply materials and replace heating c o i l . - Supply materials and replace corroded roof truss members - Paint tank internally and externally.

Read more
January 2004 to July 2004

KOT/ KOSF EMERGENCY REPLACEMENT OF PRODUCT PIPELINES.

Client: KENYA PIPELINE CORPORATION

Contract Value: USD 800,000

- Installation of the 16” dia. Ago, 12” dia. MSP and 12” dia. KERO Pipelines from KOT to KOSF ps.14 approx. 1.0 km each - Procurement of pipes and fittings. - Excavation and casting of pipe supports. - Fabricate, weld and install new lines on concrete support. - Tie - in new lines to existing facilities. - Grit blast and paint externally all the pipes & f i t t i n g s . - Commissioning of new lines.

Read more
October 2003 to March 2004

MECHANICAL REHABILITATION TO T. 606

Client: KENYA PETROLEUM REFINERIES LIMITED

Contract Value: USD 200,000

gas free, clean and blast tank - Replace bottom and annular plates - Replace bitumen/ sand mix tank pad. - Replace 5th and 6th shell courses. - Renew condemned roof trusses. - Replace existing sand bitumen mix tank pad shoulder with concrete.

Read more
February 2003 to December 2003

MECHANICAL REHABILITATION TO T. 103.

Client: KENYA PETROLEUM REFINERIES

Contract Value: USD 450,000

Open tank manholes and gas free the t a n k . - Clean and grit blast tank for mechanical i n s p e c t i o n - Cut and dismantle the existing old single deck floating roof. - Replace the tank annular plates with new, including the tank pad shoulder. - Procure the necessary materials to build a double deck floating roof for a 44 meters DIA & 14.63 meters. High t a n k . - Fabricate and install new double deck floating roof including refurbishing of corroded parts of the t a n k . - Grit blast and paint the tank. - Testing the Tank (Vacuum box & Hydrostatically tests) - Tank commission.

Read more